9.25.4.3.Installation of Vapour Barriers
(1) Products installed to function as the vapour barrier shall protect the warm side of wall, ceiling and floor assemblies.
(2) Where different products are used for the vapour barrier and the insulation, the vapour barrier shall be installed
sufficiently close to the warm side of the insulation to prevent condensation at design conditions. (See Notes A-
9.25.4.3.(2) and A-9.25.5.1.(1))
(3) Where the same product is used for the vapour barrier and the insulation, the product shall be installed sufficiently
close to the warm side of the assembly to prevent condensation at design conditions. (See Notes A-9.25.4.3.(2), A-
9.25.5.1.(1) and A-9.25.5.2.)
Understand this provision in seconds
BUILDAiD Assist explains any article of the building code in plain English — with exact citations, exceptions and related requirements.
Code text is reproduced for reference from the Ontario Building Code (O. Reg. 163/24, 2024 Building Code Compendium). This page is provided for general information and is not an official copy. Always verify requirements against the official Ontario Building Code and confirm with your local building department.