PART 9 — HOUSING AND SMALL BUILDINGSUpdated for the 2024 Ontario Building Code
Try BUILDAiD Beta
9.25.4.2.Vapour Barrier Materials
(1) Except as provided in Sentence (2), vapour barriers shall have a permeance not greater than 60 ng/(Pa×s×m2)
measured in accordance with ASTM E96 / E96M, “Standard Test Methods for Water Vapor Transmission of Materials,”
using the desiccant method (dry cup).
(2) Thermally insulated foundation wall assemblies are permitted to be constructed with variable-permeance vapour
barriers having a permeance not greater than 60 ng/(Pa×s×m2) using the desiccant method (dry cup) and greater than
300 ng/(Pa×s×m2) using the water method (wet cup) measured in accordance with ASTM E96 / E96M, “Standard Test
Methods for Water Vapor Transmission of Materials.” (See Note A-9.25.4.2.(2))
(3) Where the intended use of the interior space will result in high moisture generation, the assembly shall be designed
according to Part 5. (See Note A-9.25.4.2.(3))
(4) Where polyethylene is installed to serve only as the vapour barrier, it shall comply with Clause 4.4, Thermal
Stability, and Clause 5.7, Oxidative Induction Time, of CAN/CGSB-51.34-M, “Vapour Barrier, Polyethylene Sheet for
Use in Building Construction.”
(5) Membrane-type vapour barriers other than polyethylene shall conform to the requirements of CAN/CGSB-51.33-
M, “Vapour Barrier, Sheet, Excluding Polyethylene, for Use in Building Construction.”
(6) Membrane-type vapour barriers other than polyethylene that are susceptible to deterioration under prolonged
exposure to direct ultraviolet radiation shall
(a) be covered, or
(b) only be installed in locations that are not exposed to direct ultraviolet radiation after the completion of construction.
(See Note A-9.25.4.2.(6))
(7) Where a coating is applied to gypsum board to function as the vapour barrier, the permeance of the coating shall be
determined in accordance with CAN/CGSB-1.501-M, “Method for Permeance of Coated Wallboard.”
(8) Where insulation functions as the vapour barrier, it shall be sufficiently thick so as to meet the requirement of
Sentence (1).
← Previous9.25.4.1. Required Barrier to Vapour DiffusionNext →9.25.4.3. Installation of Vapour Barriers
Understand this provision in seconds
BUILDAiD Assist explains any article of the building code in plain English — with exact citations, exceptions and related requirements.
Code text is reproduced for reference from the Ontario Building Code (O. Reg. 163/24, 2024 Building Code Compendium). This page is provided for general information and is not an official copy. Always verify requirements against the official Ontario Building Code and confirm with your local building department.