9.25.3.3.Continuity of the Air Barrier System
(1) Where the air barrier system consists of an air-impermeable panel-type material, all joints shall be sealed to prevent
air leakage.
(2) Where the air barrier system consists of flexible sheet material, all joints shall be
(a) sealed with compatible material such as tape or flexible sealant, or
(b) except as required by Sentence (2.1), lapped not less than 100 mm and clamped, such as between framing members,
furring or blocking, and rigid panels.
(2.1) Where an air barrier system consisting of flexible sheet material is installed at locations where it is not supported by
an interior finish, such as a behind a bathtub, shower enclosure or fireplace, the continuity of the air barrier shall be
maintained by sealing its joints.
(3) Where an interior wall meets an exterior wall, ceiling, floor or roof required to be provided with air barrier
protection, the air barrier system shall extend across the intersection and shall be sealed in accordance with Sentences (1)
and (2).
(4) Where an interior wall projects through a ceiling or extends to become an exterior wall, spaces in the wall shall be
blocked to provide continuity across those spaces with the air barrier system in the abutting walls or ceiling by
(a) sealing each air barrier to the blocking, or
(b) wrapping each air barrier around the transition and sealing in accordance with Sentences (1) and (2).
(5) Where an interior floor projects through an exterior wall to become an exterior floor,
(a) the air barrier of the wall under the floor shall be continuous with or sealed to the subfloor or the air barrier on the
underside of the floor,
(b) the air barrier of the wall above the floor shall be continuous with or sealed to the subfloor or the air barrier on the
top of the floor, and
(c) the spaces between floor joists shall be blocked and sealed.
(5.1) Where a header wrap is used as an air barrier, it shall be sealed or lapped to the wall air barrier above and below in
accordance with Sentences (1) and (2).
(6) Penetrations of the air barrier system, such as those created by the installation of electrical wiring, electrical boxes,
piping or ductwork, shall be sealed to maintain the integrity of the air barrier system over the entire surface.
(6.1) Where an interior air barrier is penetrated by doors, windows and other fenestration, the air barrier shall be sealed to
the door frame or window frame with
(a) compatible tape, or
(b) spray foam insulation.
(6.2) Where an exterior air barrier is penetrated by doors, windows and other fenestration, the air barrier shall be sealed to
the door frame or window frame with
(a) compatible flexible flashing material,
(b) caulking, or
(c) spray foam insulation.
(7) Where access hatches and sump pit covers are installed through assemblies constructed with an air barrier system,
they shall be weatherstripped around their perimeters to prevent air leakage.
(8) Clearances between chimneys or gas vents and the surrounding construction that would permit air leakage from
within the building into a wall or attic or roof space shall be sealed by noncombustible material to prevent such leakage
and shall be sealed to the air barrier with tape or another compatible material, and to the vent with high temperature
caulking in accordance with the manufacturer’s installation instructions.
r1 (9) Reserved.
(10) Sump pit covers shall be sealed to maintain continuity of the air barrier system.
← Previous9.25.3.2. Air Barrier System Properties (See Note A-9.25.5Next →9.25.3.3A. Vapour Barriers Used as Air Barriers
Understand this provision in seconds
BUILDAiD Assist explains any article of the building code in plain English — with exact citations, exceptions and related requirements.
Code text is reproduced for reference from the Ontario Building Code (O. Reg. 163/24, 2024 Building Code Compendium). This page is provided for general information and is not an official copy. Always verify requirements against the official Ontario Building Code and confirm with your local building department.