OBC DIVISION B · PART 9 — HOUSING AND SMALL BUILDINGSUpdated for the 2024 Ontario Building Code
Try BUILDAiD Beta
Section 9.12 — Excavation
Full text of Section 9.12 (Excavation) — Division B, Part 9 (Housing and Small Buildings) of the 2024 Ontario Building Code, with every article reproduced below.
On this page:
9.12.1.1.9.12.1.2.9.12.1.3.9.12.1.4.9.12.2.1.9.12.2.2.9.12.3.1.9.12.3.2.9.12.3.3.9.12.3.4.9.12.4.1.
9.12.1.1.9.12.1.2.9.12.1.3.9.12.1.4.9.12.2.1.9.12.2.2.9.12.3.1.9.12.3.2.9.12.3.3.9.12.3.4.9.12.4.1.
9.12.1.General
9.12.1.1.Removal of Topsoil and Organic Matter permalink →
(1) The topsoil and vegetable matter in all unexcavated areas under a building shall be removed.
(2) In localities where termite infestation is known to be a problem, all stumps, roots and other wood debris shall be
removed from the soil to a depth of not less than 300 mm in unexcavated areas under a building.
(3) The bottom of every excavation shall be free of all organic material.
9.12.1.2.Standing Water permalink →
(1) Excavations shall be kept free of standing water.
9.12.1.3.Protection from Freezing permalink →
(1) The bottom of excavations shall be kept from freezing throughout the entire construction period.
9.12.1.4.Precautions During Excavation permalink →
(1) Every excavation shall be undertaken in such a manner to prevent damage to adjacent property, existing structures,
utilities, roads and sidewalks at all stages of construction.
(2) Material shall not be placed nor shall equipment be operated or placed in or adjacent to an excavation in a manner
that may endanger the integrity of the excavation or its supports.
9.12.2.Depth
9.12.2.1.Excavation to Undisturbed Soil permalink →
(1) Excavations for foundations shall extend to undisturbed soil.
9.12.2.2.Minimum Depth of Foundations permalink →
(1) Except as provided in Sentences (4) to (7), the minimum depth of foundations below finished ground level shall
conform to Table 9.12.2.2.
Table 9.12.2.2.
Minimum Depths of Foundations
Forming Part of Sentence 9.12.2.2.(1)
Minimum Depth of Foundation Containing Minimum Depth of Foundation Containing
Type of Soil Heated Basement or Crawl Space(1) No Heated Space(2)
Good Soil Drainage Poor Soil Drainage Good Soil Drainage Poor Soil Drainage
Rock No limit No limit No limit No limit
Below the depth of frost
Coarse grained soils No limit No limit No limit
penetration
Below the depth of frost Below the depth of frost
Silt No limit No limit
penetration(3) penetration
Clay or soils not 1.2 m but not less than the 1.2 m but not less than the
1.2 m(3) 1.2 m
clearly defined(4) depth of frost penetration(3) depth of frost penetration
Notes to Table 9.12.2.2.:
(1) Foundation not insulated to reduce heat loss through the footings.
(2) Including foundations insulated to reduce heat loss through the footings.
(3) Good soil drainage to not less than the depth of frost penetration.
(4) See Note A-Table 9.12.2.2.
(2) Where a foundation is insulated in a manner that will reduce the heat flow to the soil beneath the footings, the
foundation depth shall conform to that required for foundations containing no heated space. (See Note A-9.12.2.2.(2))
(3) The minimum depth of foundations for exterior concrete steps with more than 2 risers shall conform to
Sentences (1), (2) and (5).
(4) Concrete steps with 1 and 2 risers are permitted to be laid on ground level.
(5) The foundation depths required in Sentence (1) are permitted to be decreased where experience with local soil
conditions shows that lesser depths are satisfactory, or where the foundation is designed for lesser depths.
(6) The foundation depths required in Sentence (1) do not apply to foundations for
(a) buildings
(i) that are not of masonry or masonry veneer construction, and
(ii) whose superstructure conforms with the requirements of the deformation resistance test in CSA Z240.2.1,
“Structural requirements for manufactured homes,” or
(b) accessory buildings
(i) that are not of masonry or masonry veneer construction,
(ii) not more than 1 storey in building height,
(iii) not more than 55 m² in building area, and
(iv) where the distance from finished ground to the underside of the floor joists is not more than 600 mm.
(7) The foundation depths required by Sentence (1) do not apply to foundations for decks and other accessible exterior
platforms
(a) of not more than 1 storey,
(b) not more than 55 m² in area,
(c) where the distance from finished ground to the underside of the floor joists is not more than 600 mm,
(d) not supporting a roof, and
(e) not attached to another structure, unless it can be demonstrated that differential movement will not adversely affect
the performance of that structure.
This provision includes a table — formatting is preserved from the source; refer to the official code for the authoritative layout.
9.12.3.Backfill
9.12.3.1.Placement of Backfill permalink →
(1) Backfill shall be placed to avoid damaging the foundation wall, the drainage tile, drainage layer, externally applied
thermal insulation, waterproofing and dampproofing of the wall.
9.12.3.2.Grading of Backfill permalink →
(1) Backfill shall be graded to prevent drainage towards the foundation after settling.
9.12.3.3.Deleterious Debris and Boulders permalink →
(1) Backfill that is within 600 mm of the foundation shall be free of deleterious debris and boulders larger than 250 mm
diam. (See Note A-9.12.3.3.(1))
(2) Except as permitted in Sentence (3), backfill shall not contain pyritic material or material that is susceptible to ice
lensing in concentrations that will damage the building to a degree that would adversely affect its stability or the
performance of assemblies separating dissimilar environments. (See Note A-9.4.4.4.(1))
(3) Backfill with material of any concentration that is susceptible to ice lensing is permitted where foundation walls are
(a) cast-in-place concrete,
(b) concrete block insulated on the exterior, or
(c) concrete block protected from the backfill by a material that serves as a slip plane.
(See Note A-9.4.4.4.(1))
9.12.3.4.Lateral Support of Foundation Wall permalink →
(1) Where the height of foundation wall is such that lateral support is required, or where the required concrete strength
of the wall has not been reached, the wall shall be braced or laterally supported before backfilling.
9.12.4.Trenches Beneath Footings
9.12.4.1.Support of Footings permalink →
(1) The soil in trenches beneath footings for sewers and watermains shall be compacted by tamping up to the level of
the footing base, or shall be filled with concrete having a strength not less than 10 MPa to support the footing.
Understand any provision in seconds
BUILDAiD Assist explains any article of the building code in plain English — with exact citations, exceptions and related requirements.
Code text is reproduced for reference from the Ontario Building Code (O. Reg. 163/24, 2024 Building Code Compendium). This page is provided for general information and is not an official copy. Always verify requirements against the official Ontario Building Code and confirm with your local building department.