1.3.3.4.Occupancy Permit — Certain Buildings of Residential Occupancy
(1) No person shall occupy or permit to be occupied a building described in Sentence (3), or part of it, unless the chief
building official or a person designated by the chief building official has issued a permit authorizing occupation of the
building or part of it in accordance with Sentence (4).
(2) This Article does not apply in respect of the occupancy of an existing building, or part of it, that has been subject to
extension or material alteration or repair.
(3) A building referred to in Sentence (1) is a building intended for residential occupancy that,
(a) is of three or fewer storeys in building height and has a building area not exceeding 600 m²,
(b) has no accommodation for tourists,
(c) does not have a dwelling unit above another dwelling unit,
(d) does not have any dwelling units sharing a common means of egress, and
(e) does not contain a retirement home.
(4) The chief building official or a person designated by the chief building official shall issue a permit authorizing
occupation of a building described in Sentence (3), where,
(a) the structure of the building with respect to the dwelling unit to be occupied is substantially complete and ready to
be used for its intended purpose,
(b) the building envelope, including, but not limited to, cladding, roofing, windows, doors, assemblies requiring fire-
resistance ratings, closures, insulation, vapour barriers and air barriers, with respect to the dwelling unit to be
occupied, is substantially complete,
(c) the walls enclosing the dwelling unit to be occupied conform to Sentence 9.25.2.3.(7) of Division B,
(d) required electrical supply is provided for the dwelling unit to be occupied,
(e) required firefighting access routes to the building have been provided and are accessible,
(f) the following building components and systems are complete and operational for the dwelling unit to be occupied:
(i) required exits, floor access and egress systems, handrails, guards, smoke alarms, carbon monoxide alarms and
fire separations, including, but not limited to, fire stops,
(ii) required exhaust fume barriers and self-closing devices on doors between an attached or built-in garage and
the dwelling unit,
(iii) water supply, sewage disposal, lighting and heating systems, and
(iv) protection of foamed plastics required by Article 9.10.17.10. of Division B,
(g) the following building components and systems are complete, operational and tested for the dwelling unit to be
occupied:
(i) water system,
(ii) building drain and building sewer, and
(iii) drainage system and venting system,
(h) required plumbing fixtures in the dwelling unit to be occupied are substantially complete and operational, and
(i) where applicable, the building conforms to Article 9.1.1.7. of Division B with respect to the dwelling unit to be
occupied.
(5) Where a registered code agency has been appointed to perform the functions described in clause 4.1(4)(b) or (c) of
the Act in respect of the construction of a building described in Sentence (3), the chief building official or a person
designated by the chief building official shall issue the permit referred to in Sentence (4) after receipt of a certificate for
the occupancy of a building described in Sentence 1.3.3.4.(3) of Division C issued by the registered code agency in
respect of the building.
(6) Where applicable, the chief building official or a person designated by the chief building official shall not issue a
permit authorizing occupation of the building or part of it, unless compliance with section 168.3.1 of the Environmental
Protection Act has been achieved.
Understand this provision in seconds
BUILDAiD Assist explains any article of the building code in plain English — with exact citations, exceptions and related requirements.
Code text is reproduced for reference from the Ontario Building Code (O. Reg. 163/24, 2024 Building Code Compendium). This page is provided for general information and is not an official copy. Always verify requirements against the official Ontario Building Code and confirm with your local building department.