7.3.6.1.Tests and Inspection of Drainage or Venting Systems
(1) Except in the case of an external leader, after a section of drainage system or a venting system has been roughed in,
and before any fixture is installed or piping is covered, a water or an air test shall be conducted.
(2) After every fixture is installed and before any part of the drainage system or venting system is placed in operation, a
final test shall be carried out when requested by the chief building official.
(3) Where a prefabricated system is assembled off the building site in such a manner that it cannot be inspected and
tested on site, off-site inspections and tests shall be conducted.
(4) Where a prefabricated system is installed as part of a drainage system or venting system, all other plumbing work
shall be tested and inspected and a final test shall be carried out on the complete system when requested.
(5) A ball test shall be carried out on a sanitary building drain, sanitary building sewer, storm building drain and a
storm building sewer buried underground.
(6) A sewer lateral extension need not be tested and inspected if the sewer lateral extension was constructed, tested and
inspected at the time of the installation of the public sewer.
← Previous7.3.5.6. Spatial Separation (See Note A-7.3.5.6.)Next →7.3.6.2. Tests of Pipes in Drainage Systems
Understand this provision in seconds
BUILDAiD Assist explains any article of the building code in plain English — with exact citations, exceptions and related requirements.
Code text is reproduced for reference from the Ontario Building Code (O. Reg. 163/24, 2024 Building Code Compendium). This page is provided for general information and is not an official copy. Always verify requirements against the official Ontario Building Code and confirm with your local building department.