PART 4 — STRUCTURAL DESIGNUpdated for the 2024 Ontario Building Code
Try BUILDAiD Beta
4.2.2.3.Field Review
(1) A field review shall be carried out by the designer or by another suitably qualified person to ascertain that the
subsurface conditions are consistent with the design and that construction is carried out in accordance with the design and
good engineering practice. (See Note A-4.2.2.3.(1))
(2) The review required by Sentence (1) shall be carried out
(a) on a continuous basis
(i) during the construction of all deep foundation units with all pertinent information recorded for each foundation
unit,
(ii) during the installation and removal of retaining structures and related backfilling operations, and
(iii) during the placement of engineered fills that are to be used to support the foundation units, and
(b) as required, unless otherwise directed by the chief building official,
(i) in the construction of all shallow foundation units, and
(ii) in excavating, dewatering and other related works.
Understand this provision in seconds
BUILDAiD Assist explains any article of the building code in plain English — with exact citations, exceptions and related requirements.
Code text is reproduced for reference from the Ontario Building Code (O. Reg. 163/24, 2024 Building Code Compendium). This page is provided for general information and is not an official copy. Always verify requirements against the official Ontario Building Code and confirm with your local building department.