PART 3 — FIRE PROTECTION, OCCUPANT SAFETY AND ACCESSIBILITYUpdated for the 2024 Ontario Building Code
Try BUILDAiD Beta
3.2.2.92.Group F, Division 3, Storage Garages up to 22 m High
(1) A building used as a storage garage with all storeys constructed as open-air storeys and having no other occupancy
above it is permitted to have its floor, wall, ceiling and roof assemblies constructed without a fire-resistance rating
provided it is
(a) of noncombustible construction,
(b) not more than 22 m high, measured between grade and the ceiling level of the top storey,
(c) not more than 10 000 m2 in building area, and
(d) designed so that every portion of each floor area is within 60 m of an exterior wall opening.
r1 3.2.2.93. Encapsulated Mass Timber Construction, Various Occupancies, Heights
and Areas, Sprinklered
(1) A building that is classified as Group A, Division 2, Group B, Division 3, Group C other than a retirement home,
Group D, Group E, or Group F, Division 2 or 3, is permitted to conform to Sentence (2) provided
(a) except as permitted by Sentences 3.2.2.7.(1) and 3.2.2.18.(2), the building is sprinklered throughout,
(b) the building has a building height not exceeding the number of storeys shown in Table 3.2.2.93. for the applicable
major occupancy and minimum encapsulation rating,
(c) the building has a maximum height that conforms to the value shown in Table 3.2.2.93. for the applicable major
occupancy and minimum encapsulation rating that is measured between the floor of the first storey and the
uppermost floor level that does not serve a rooftop enclosure for elevator machinery, a stairway or a service room
used only for service to the building,
(d) the building has a maximum building area that conforms to the value shown in Table 3.2.2.93. for the applicable
major occupancy, and
(e) except as provided in Sentences 3.1.6.3.(4) and 3.1.6.7.(1) and Article 3.1.6.4., the encapsulation rating conforms to
the value shown in Table 3.2.2.93. for the applicable major occupancy and maximum building height.
(See Note A-3.2.2.93.(1) and Table 3.2.2.93. See also Articles 3.2.2.48. and 3.2.2.57.)
(2) Except as provided in Article 3.2.2.16., the building referred to in Sentence (1) is permitted to be of encapsulated
mass timber construction or noncombustible construction used singly or in combination, and,
(a) except as provided in Sentence (3), floor assemblies shall be fire separations with a fire-resistance rating not less
than 2 h,
(b) mezzanines shall have a fire-resistance rating not less than 1 h, and
(c) loadbearing walls, columns and arches shall have a fire-resistance rating not less than that required for the
supported assembly.
(3) In a building classified as a Group C major occupancy that contains dwelling units that have more than one storey,
subject to the requirements of Sentence 3.3.4.2.(3), the floor assemblies, including floors over basements, that are entirely
contained within these dwelling units shall have a fire-resistance rating not less than 1 h but need not be constructed as
fire separations.
(4) In buildings referred to in Sentence (1) where the roof assembly of an exit stairway or vertical service space used as
an elevator hoistway has a height greater than 55 m measured from grade to the highest point of the roof assembly, the
enclosure for the stairway or hoistway shall be of encapsulated mass timber construction or constructed of concrete.
(5) Group E major occupancies and storage garages located in a building or part thereof within the scope of this Article
are permitted to be constructed in accordance with this Article and the corresponding Group A, Division 2, Group C, or
Group D major occupancy requirements contained in Table 3.2.2.93., provided
(a) the Group E major occupancy is located below the third storey, and
(b) the storage garage is located below the fifth storey. (See also Article 4.4.2.1.)
(See Note A-3.2.2.48.(4), 3.2.2.57.(3) and 3.2.2.93.(5) to (7))
(6) Group A, Division 2 major occupancies located in a building or part of a building within the scope of this Article
are permitted to be constructed in accordance with this Article and the corresponding Group C, or Group D major
occupancy requirements contained in Table 3.2.2.93., provided they are located below the fourth storey.
(See Note A-3.2.2.48.(4), 3.2.2.57.(3) and 3.2.2.93.(5) to (7))
(7) Group F, Division 2 and 3 major occupancies located in a building or part thereof within the scope of this Article
are permitted to be constructed in accordance with this Article and the corresponding Group D major occupancy
requirements contained in Table 3.2.2.93., provided they are located below the third storey.
(See Note A-3.2.2.48.(4), 3.2.2.57.(3) and 3.2.2.93.(5) to (7))
Table 3.2.2.93.
Encapsulated Mass Timber Construction, Various Occupancies, Heights and Areas, Sprinklered(1)(2)
Forming Part of Sentences 3.2.2.93.(1), (5), (6) and (7)
Maximum Building Maximum Building Area, Minimum Encapsulation
Major Occupancy Maximum Height, m
Height, Storeys m2 Rating, min
18 76 70
Group A, Division 2 12 51 7200 50
6 26 0
10 42 70
Group B, Division 3 6 26 8000 50
4 17 0
18 76 70
Group C 6000
8 34 0
18 76 70
Group D 7200
9 38 0
12 51 70
Group E 8 34 6000 50
6 26 0
10 42 70
Group F, Division 2 7 30 4500 50
5 21 0
12 51 70
Group F, Division 3 8 34 7200 50
5 21 0
Notes to Table 3.2.2.93.:
(1) See Sentences (5) to (7) and Articles 3.2.2.4. to 3.2.2.8. for information pertaining to multiple major occupancies.
(2) Linear interpolation is not permitted in using Table 3.2.2.93.
Division B – Part 3 86a
This provision includes a table — formatting is preserved from the source; refer to the official code for the authoritative layout.
← Previous3.2.2.91. Group F, Division 3, One Storey, Any Area, Low FNext →3.2.3.1. Limiting Distance and Area of Unprotected Openin
Understand this provision in seconds
BUILDAiD Assist explains any article of the building code in plain English — with exact citations, exceptions and related requirements.
Code text is reproduced for reference from the Ontario Building Code (O. Reg. 163/24, 2024 Building Code Compendium). This page is provided for general information and is not an official copy. Always verify requirements against the official Ontario Building Code and confirm with your local building department.